New Transmission Line To Sherco Plant In Becker Approved
MINNEAPOLIS (WJON News) -- Building of a new major Minnesota utility line has been approved. Xcel Energy has received approval from the state on the 175-mile Minnesota Energy Connection transmission line.
Once completed in 2028 the line will carry electricity generated in southwest Minnesota to the electric grid at the Sherco site in Becker. The line will deliver energy to power over 1 million homes across the Upper Midwest. Xcel Energy says the new line continues its investment in the Becker community and positions southwest Minnesota for significant new investments in the future. Xcel will now begin working on design, engineering, and negotiations with landowners to purchase easements where the transmission line will be built.

Construction is scheduled to start in early 2026 and finish in 2028 with additional substation construction taking place through 2031. Xcel Energy also received approval on a new natural gas-fired power plant near the southern point of the line in Lyon County.
READ MORE FROM AUTHOR PAUL HABSTRITT:
- Stefan’s Dream Wins 5th Consecutive KVSC Trivia Title
- Sartell Police Chief Silgjord Is Now City’s Public Safety Director
- A Hauntingly Good Time Coming To St. Cloud This Weekend
- Children’s Theatre Star Brings Message Of Hope To New Production
- How Sweet It Is, WJON Show Celebrates One Year Anniversary
- 2024 Another Impactful Season For The Ledge Amphitheater
LOOK: Here are the 50 best beach towns in America
Gallery Credit: Keri Wiginton
LOOK: See the iconic cars that debuted the year you were born
LOOK: Famous Historic Homes in Every State
More From 1390 Granite City Sports